Q2 2025
Completion of construction
Август 2024
- Завершили установку скоростных бесшумных лифтов.
- Выполнили работы по утеплению кровли на 80%.
- Продолжили подготовку фасада к монтажу декоративных элементов: рустов, пилястр и карнизов.
- В квартирах начали установку канализационных труб, стояков водоснабжения и отопления.
- Выполнили работы по черновой отделке лифтовых холлов на 55%.
- Установили конструкции въезда на автоматический паркинг.
- В историческом павильоне приступили к монолитным работам и гидроизоляции фундамента. Здесь появится Clubhouse только для жителей с пространством Lounge, патио, фитнесом и детской игровой комнатой.
JULY 2024
- A sample of an elevator hall was created on the construction site.
- The historical facade was reinforced by injection.
- The alignment of the exterior walls was commenced.
- Plastering works on the stairwells were completed.
- Stoneworks on the walls on the top floor were commenced.
- 75% of the elevator equipment was installed.
- Installation of air ducts and electrical trays was continued.
- Installation of sewerage stacks was commenced.
- The slab between the minus second and minus third levels of the parking was filled by 75%.
JUNE 2024
- Reinforcement and concreting of the minus second level of the parking was continued.
- Plastering works on staircases were completed by 50%.
- Installation of air ducts was commenced.
- The elevator equipment was installed by 35%.
- Communication networks were brought to the house: Internet, telephone, television.
- 95% of the facade was reinforced by injection.
- The monolithic structures of the last floor were completed.
- Installation of the roof was commenced.
- Preparation of the territory of the house for landscaping was commenced: the location of the paths was being planned.
MAY 2024
- 95% of the monolith terraces were filled in.
- The vertical structures of the top floor were erected and the construction of its slabs was commenced.
- Preparation for plastering works was continued - 50% of the facade was reinforced by injection.
- The metal spacer system was disassembled by 95%.
- Installation of the brick walls of the elevator halls of the five floors of the house was completed.
APRIL 2024
- The metal spacer system was dismantled by 90%, which added stability to the building during the dismantling of old floor slabs.
- The walls of the elevator shafts were completed.
- The vertical structures of the sixth floor were fully completed, and the slab was completed by 45%.
- The brick walls of the elevator halls of the five floors of the house were erected by 90%.
- In the left wing, the rough finishing and installation of the engineering systems for the fire escape and elevator hall were commenced.
- Waterproofing of the walls on the minus first level of the parking was completed by 80%.
MARCH 2024
- Brick walls and partitions of the first floor were erected by 35%.
- Reinforcing of the floor slab was commenced and the vertical structures of the sixth floor were completed by 93%.
- The metal spacer system was dismantled by 80%.
- 70% of the elevator shafts were equipped.
- Waterproofing of the walls of the first level of the parking was installed by 70%.
- The space for the second level of the parking was prepared by 90%.
FEBRUARY 2024
- Dismantling of the metal spacer system was commenced.
- Construction of brick walls and partitions on the first floor was commenced.
- Brick partitions on the fourth floor were erected by 10%.
- The slab of the fourth floor was completed by 90%, the fifth floor - by 81%.
- Waterproofing of the walls of the first level of the parking was completed by 52%.
- The second level of the parking was completed by 80%.
JANUARY 2024
- The brick walls of the inter-apartment corridors on the third floor were erected by 50%.
- Construction of brick partitions on the fourth floor was commenced.
- The slab of the fourth floor was completed by 80%, the fifth floor - by 35%.
- Installation of balconies and loggias was continued.
- Installed waterproofing of the walls of the first level of the parking by 30%.
- Construction of the second level of the parking was continued.
DECEMBER 2023
- Brick walls of the inter-apartment corridors on the second floor were erected by 75%.
- Construction of brick partitions on the third floor was commenced.
- The slab of the fourth floor was completed by 75%.
- Construction of the first balconies was continued.
- A reinforcement frame for the fifth floor was created.
- Inter-apartment walls of monolithic concrete on the fifth floor were being erected.
- The second level of the parking was being constructed.
NOVEMBER 2023
- The slab of the fourth floor was completed by 65%.
- Construction of brick partitions on the second floor was commenced.
- Construction of the first balconies was commenced.
- Construction of the slab of the minus first floor of the parking was completed by 95%.
OCTOBER 2023
- The slab of the second floor was completed by 80%. Construction of the third floor was commenced: the monolithic frame was filled, 50% of the columns and walls were built, 30% of the floor slab was prepared. The stonework was commenced.
- Works in the parking were continued. Waterproofing of the walls was being made.
SEPTEMBER 2023
- The second aboveground floor of the house was being erected. The monolithic frame was being filled, 40% of the columns and walls were built, 30% of the floor slab was reinforced.
- A multi-level underground parking was being built. The base of the floor slab was constructed and waterproofing of the walls was being made.
AUGUST 2023
- Monolithic structures of the ground floor and lobby were being erected.
- Reinforcement of the walls of the second floor was commenced.
- The heating system was put into the building.
- Installation of the floor slab of the second floor in the parking was commenced and excavation of the ground of the first floor was at the completion stage - 3,115 cubic meters of soil were removed.
JULY 2023
- Floor covering of the first floor was commenced.
- Excavation works under the transfer plate for the installation of automated underground parking were carried out.
- Injecting of the existing brick walls with hydrophobic compounds was commenced - this will ensure the water resistance of the structures.
JUNE 2023
MAY 2023
APRIL 2023
MARCH 2023
FEBRUARY 2023
JANUARY 2023
DECEMBER 2022
NOVEMBER 2022
OCTOBER 2022
SEPTEMBER 2022
AUGUST 2022
JULY 2022
JUNE 2022
MAY 2022
APRIL 2022
MARCH 2022
Август 2024
JUNE 2024 2024
APRIL 2024 2024
FEBRUARY 2024 2024
JANUARY 2024 2024
DECEMBER 2023 2023
NOVEMBER 2023 2023
OCTOBER 2023 2023
SEPTEMBER 2023 2023
AUGUST 2023 2023
JULY 2023 2023
JUNE 2023 2023
MAY 2023 2023
APRIL 2023 2023
MARCH 2023 2023
FEBRUARY 2023 2023
JANUARY 2023 2023
DECEMBER 2022 2022
NOVEMBER 2022 2022
OCTOBER 2022 2022
SEPTEMBER 2022 2022
AUGUST 2022 2022
JULY 2022 2022
JUNE 2022 2022
MAY 2022 2022
APRIL 2022 2022
MARCH 2022 2022